Construction of the Moegão complex has reached 80.29% completion, according to technical measurements taken in the first half of December. The project will centralize the reception of trains loaded with solid vegetable bulk cargo at the Paraná ports and will distribute the cargo to 11 terminals that will be interconnected to the system.
The Government of the State of Paraná, through Portos do Paraná, is investing more than R$ 650 million in the construction of the complex, using its own resources and financing from the National Bank for Economic and Social Development (BNDES).
To date, 87% of the civil works (physical structure), 85.24% of the mechanical works, and 57.81% of the electrical works have been completed. According to the schedule, completion is expected in early February 2026.
The teams are also working on finalizing the installation of the Fire Prevention and Fighting Systems (SPCI) and the Lightning Protection System (SPDA). Among the next steps are the automation of the complex, the performance of safety tests on all systems, and the construction of the power substation, which will be dedicated to the Moegão.
“The Moegão will revolutionize Paraná’s rail logistics and benefit the community. It is a project being 100% funded by Portos do Paraná, and we are certain that it will bring important results,” says the CEO of Portos do Paraná, Luiz Fernando Garcia.
When operational, the project will have the capacity to receive 24 million tons of grains and meals per year, serving the terminals of the East Export Corridor (Corex). Currently, about 550 wagons are unloaded daily at the export terminals.
With the completion of the project, this process will be standardized at a single unloading point with the movement of 900 wagons per day. The bulk agricultural products will travel via conveyor belts to 11 terminals interconnected to the system and, from there, to the ships.
“This will be phenomenal; the Moegão will be able to handle up to 68,000 tons per day. It’s a huge capacity for receiving products. Portos do Paraná is raising the bar in terms of bulk cargo handling in the rail modal,” emphasized Diego Weber Rafaeli, contracts manager at Tucumann, one of the four engineering companies executing the project. The other three are TMSA, Zortea, and Engeluz.
In addition to increased productivity, there will also be advantages in local traffic. The train sets will no longer need to enter the warehouses to unload, and maneuvering will be eliminated. The number of crossings with interruptions on the access roads to the port area will drop from 16 to five.
Extensive expansion planning
The Moegão is not an isolated structure. The project is part of a set of works and investments that are transforming the Port of Paranaguá, a world reference in operational efficiency.
In April of this year, Portos do Paraná completed the regularization of all leasable areas through auctions, guaranteeing legal security for public-private partnerships and enabling significant investments for the modernization and expansion of port infrastructure. In total, nine auctions have already resulted in R$ 5.7 billion in investments and another R$ 1.1 billion in concessions.
“T” shaped pier
The auctions of PARs 14, 15 and 25 will guarantee the construction of the “T” shaped pier. Of the total R$ 2.2 billion that the lessees will invest, R$ 1.2 billion will be allocated to the project, which will have four new berths. In addition, the State Government will make an additional contribution of R$ 1 billion. The new pier will feature an ultramodern conveyor belt system that will transport products from the terminals to the ships’ holds at high speed. The current system handles approximately 3,000 tons of soybeans per hour; with the new structure, this volume will increase to 8,000 tons per hour.
The vessels will also be larger than the current ones, allowing for increased cargo handling, reduced operating costs, and increased competitiveness for the port.
Access Channel
The reception of larger ships will only be possible thanks to the concession of the access channel, granted on October 22nd through an auction at B3 in São Paulo. The winning consortium will have to deepen the channel, allowing for an increase in the draft — the distance between the deepest point of the ship and the water surface — from the current 13.3 meters to 15.5 meters within five years.
Currently, ships carry up to 78,000 tons of grains or animal feed. With the new draft, each vessel will be able to leave Paraná carrying up to 125,000 tons. “This is a significant gain in the competitiveness of the Port of Paranaguá,” highlights Garcia.
With the concession, maritime access to the Port will also feature the VTMIS (Vessel Traffic Management and Information System), which guarantees greater safety for navigation, human life, and the environment.
The installation of the VTMIS will also bring important benefits to the work of the pilots, professionals responsible for guiding ships from the entrance of the channel to docking, making the process even more agile and safe.
Source: Portos do Paraná